[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123962,791,2,"多选题","加快井巷工程关键路线施工速度的主要措施包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","全面规划、统筹安排，特别要仔细安排矿、土、安相互交叉影响大的工序 内容",true,{"key":16,"text":17,"correct":14},"B","采取多头作业、平行交叉作业，积极推广先进技术，提高井巷工程单进水平",{"key":19,"text":20,"correct":21},"C","把施工水平高、装备精良的掘进队放在重大工程上，确保工程的施工质量",false,{"key":23,"text":24,"correct":14},"D","关键路线上各工程开工，要充分做好各项施工准备工作，确保工程连续施工",{"key":26,"text":27,"correct":14},"E","加强综合平衡，使用网络技术动态实施管理","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]