[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123960":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123960,791,2,"多选题","关于进度拖延的事后控制措施，以下说法正确的是（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","对引起进度拖延的原因采取措施",true,{"key":16,"text":17,"correct":14},"B","投入更多的资源加速活动",{"key":19,"text":20,"correct":14},"C","采取措施保证后期的活动按计划执行",{"key":22,"text":23,"correct":14},"D","分析进度网络，找出有工期延迟的路径",{"key":25,"text":26,"correct":27},"E","严格控制工序，掌握现场施工实际情况，为计划实施的检査、分析、调整、总结提供原始资料",false,"ABCD","对于选项E所描述的内容，是进度控制的一般性措施。 进度拖延的事后控制措施，还包括： 1征得业主的同意后，缩小工程的范围，包括减少工作量或删去一些工作包(或分项工程)； 2改进方法和技术，提高劳动生产率； 3.采用外包策略，让更专业的公司用更快的速度、更低的成本完成一些分项工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]