[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123959":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123959,791,2,"多选题","矿业工程施工中，进度控制的一般性措施包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","突出关键路线",true,{"key":16,"text":17,"correct":14},"B","加强生产要素的配置管理",{"key":19,"text":20,"correct":14},"C","严格控制工序",{"key":22,"text":23,"correct":24},"D","投入更多的资金",false,{"key":26,"text":27,"correct":24},"E","加强施工质量管理","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]