[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123958":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123958,791,2,"多选题","井巷工程的关键线路工期决定着矿井的建设工期，加快关键线路上各工作的施工 方法和措施是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","优化矿井设计",false,{"key":16,"text":17,"correct":18},"B","合理安排关键工作的开工顺序，采用新技术、新装备、新工艺，加快施工速度",true,{"key":20,"text":21,"correct":18},"C","把技术过硬，机械装备先进的重点队伍安排在关键线路上施工",{"key":23,"text":24,"correct":18},"D","利用措施工程来缩短主要矛盾线的长度",{"key":26,"text":27,"correct":18},"E","加强综合平衡，搞好工序衔接，缩短辅助时间","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]