[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123956":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123956,791,2,"多选题","以下关于矿山工程进度的说法，不正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","把工期目标定得很高，相应地投资就要增加或质量要求适当降低",false,{"key":16,"text":17,"correct":14},"B","如果对质量要求较高，就要投入较多的资金和花费较长的建设时间",{"key":19,"text":20,"correct":21},"C","井巷工程关键线路对矿井的建设工期没有决定作用",true,{"key":23,"text":24,"correct":21},"D","高瓦斯矿井宜采用上山掘进",{"key":26,"text":27,"correct":14},"E","把重点队和技术力量过硬的施工队，放在关键线路上施工可以缩短工期","CD","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]