[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123941":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123941,791,2,"多选题","与掘进循环的总时间相关的因素包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","排水时间",false,{"key":16,"text":17,"correct":18},"B","装岩工作时间",true,{"key":20,"text":21,"correct":18},"C","钻眼工作时间",{"key":23,"text":24,"correct":18},"D","装药、连线时间",{"key":26,"text":27,"correct":18},"E","放炮通风时间","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]