[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123931,791,2,"多选题","关于掘、砌单行作业中的短段掘、砌单行作业，以下说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","短段掘、砌单行作业是在5~8 m (应与模板高度一致)较小的段高内，掘进后，即进行永久支护，不用临时支护",false,{"key":16,"text":17,"correct":18},"B","为便于下一循环的打眼工作，爆破后，矸石暂不全部清除",true,{"key":20,"text":21,"correct":18},"C","砌壁时，立模、稳模和浇灌混凝土都在浮矸上进行",{"key":23,"text":24,"correct":18},"D","短段掘、砌单行作业的优点是不需要临时支护，降低成本和工期，缺点是井壁的混凝土接茬缝比较多",{"key":26,"text":27,"correct":18},"E","随着井壁混凝土浇筑技术的提高，接茬缝的质量大大提高，而且一般在井筒施工完毕后进行壁后注浆封水，短段掘、砌单行作业的缺点基本得到克服，该作业方式成为目前最常见的立井施工作业方式","BCDE","短段掘、砌单行作业是在2~5 m (应与模板高度一致)较小的段高内，掘进后，即进行永久支护，不用临时支护。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]