[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123928":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123928,791,2,"多选题","若井筒采用现浇混凝土井壁结构，工作面浇注的混凝土可采用（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","吊桶下放混凝土",true,{"key":16,"text":17,"correct":18},"B","罐笼下放混凝土",false,{"key":20,"text":21,"correct":14},"C","管路下放混凝土",{"key":23,"text":24,"correct":18},"D","箕斗下放混凝土",{"key":26,"text":27,"correct":18},"E","矿车下放混凝土","AC","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]