[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123927":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123927,791,2,"多选题","井筒如采用工作面预注浆方法进行防治水，则应该遵守的规定有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","注浆施工前，必须编制注桨工程设计",true,{"key":16,"text":17,"correct":14},"B","注浆段长度必须大于注浆的含水岩层的厚度，并深入到不透水岩层或硬岩层5 ~10m",{"key":19,"text":20,"correct":14},"C","注浆过程中，注浆压力突然上升时必须停止注浆泵运转，卸压后方可处理",{"key":22,"text":23,"correct":24},"D","注浆结束后，便可开凿井筒",false,{"key":26,"text":27,"correct":14},"E","注浆前在含水层上方，必须按设计要求设置止浆岩帽或混凝土止浆垫","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]