[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123833":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123833,791,2,"多选题","关于露天深孔台阶爆破钻孔施工，以下说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钻机平台宽度不得小于4~6 m ，保证一次布孔不少于3排。",false,{"key":16,"text":17,"correct":18},"B","平台施工可采用浅孔爆破和推土机整平的方法",true,{"key":20,"text":21,"correct":18},"C","露天深孔台阶爆破一般采用潜孔钻机或牙轮钻机钻孔。钻孔要领是：软岩慢打，硬岩快打；小风压顶着打，不见硬岩不加压；勤看勤听勤检査",{"key":23,"text":24,"correct":18},"D","炮孔验收的主要内容有：检査炮孔深度和孔网参数；复核前排各炮孔的抵抗线；查看孔中含水情况",{"key":26,"text":27,"correct":18},"E","在炮孔验收过程中发现堵孔、深度不够时，应及时进行补钻","BCDE","钻机平台宽度不得小于6~8 m ，保证一次布孔不少于2 排。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]