[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123820":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1123820,791,2,"多选题","关于贯通测量的施测技术要求，以下说法正确的是（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","注意原始资料的可靠性，起算数据应当准确无误。各项测量工作都要有可靠的独立检核。精度要求很高的重要贯通，要采取提高精度的相应措施。",true,{"key":16,"text":17,"correct":14},"B","随贯通巷道的掘进，要及时进行测量和填图，并将测量成果及时通报施工部门，调整巷道掘进的方向和坡度",{"key":19,"text":20,"correct":14},"C","对施测成果要及时进行精度分析，必要时要进行返工重测。施测过程中，要进一步完善和充实预定的方案",{"key":22,"text":23,"correct":14},"D","贯通测量至少应独立进行两次，取平均值作为最终值，最后一次标定贯通方向时，未掘的巷道长度不得小于5 0 m",{"key":25,"text":26,"correct":14},"E","贯通工程剩余巷道距离在岩巷中剩余下15~20 m 时，测量负责人应以书面形式报告有关领导，并通知安检施工区队长","ABCDE","贯通测量至少应独立进行两次，取平均值作为最终值，最后一次标定贯通方向时，未掘的巷道长度不得大于5 0 m。@##",{"id":6,"name":30,"category":31,"favorite":32},"二建矿业工程实务","建筑工程",0]