[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1123810,791,2,"多选题","关于贯通测量的工作步骤，以下说法正确的是（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","准备工作：调査了解待贯通井巷的实际情况，根据贯通的容许偏差，选择合理的测量方案与测量方法。对重要的贯通工程，要编制贯通测量设计书，进行贯通测量误差预计，以验证所选择的测量方案、测量仪器和方法的合理性",true,{"key":16,"text":17,"correct":14},"B","施测和计算：依据选定的方案和方法进行施测和计算，每一施测和计算环节均须有独立可靠的检核，并要将施测的实际测量精度与原设计的要求精度进行比较，不符合要求应当返工重测",{"key":19,"text":20,"correct":14},"C","根据有关数据计算贯通巷道的标定几何要素，并实地标定巷道的中线和腰线。",{"key":22,"text":23,"correct":24},"D","根据掘进巷道的需要，及时延长巷道的中线和腰线，定期进行检查测量和填图，并按照测量结果及时调整基准点和腰线",false,{"key":26,"text":27,"correct":14},"E","巷道贯通之后，应立即测量出实际的贯通偏差值，并将两端的导线连接起来，计算各项闭合差。此外，还应对最后一段巷道的中腰线进行调整","ABCE","根据掘进巷道的需要，及时延长巷道的中线和腰线，定期进行检查测量和填图，并按照测量结果及时调整中线和腰线。",{"id":6,"name":31,"category":32,"favorite":33},"二建矿业工程实务","建筑工程",0]