[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123722,791,1,"单选题","立井井筒表土段采用冻结法施工时，其水文观测孔应该布置在（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","井筒掘进断面内",true,{"key":16,"text":17,"correct":18},"B","井筒冻结圈上",false,{"key":20,"text":21,"correct":18},"C","井筒掘进断面外",{"key":23,"text":24,"correct":18},"D","井筒附近","P285-288 用冻结法开凿立井井筒时，应当遵守下列规定:（1）冻结深度应当穿过风化带延深至稳定的基岩1 0 m以上。基岩段涌水较大时，应当加深冻结深度。（2）第个冻结孔应当全孔取芯，以验证井筒检查孔资料的可靠性。（3）钻进冻结孔时，必须测定钻孔的方向和偏斜度，测斜的最大间隔不得超过30m，并绘制冻结孔实际偏斜平面位置图。偏斜度超过规定时，必须及时纠正。因钻孔偏斜影响冻结效果时必须补孔。（4）水文观测孔应当打在井筒内，不得偏离井筒的净断面，其深度不得超过冻结下部隔水层。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]