[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123705,791,1,"单选题","建设单位应当在项目验收前（ ）d向管理矿山企业的主管部门、劳动行政主管部门报送矿山建设工程安全设施施工、竣工情况的综合报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","90","P266-268 矿山建设工程应当按照经批准的设计文件施工，保证施工质量;工程竣工后，应当按照国家有关规定申请验收。建设单位应当在验收前6 0日向管理矿山企业的主管部门、劳动行政主管部门报送矿山建设工程安全设施施工、竣工情况的综合报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]