[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123703,791,1,"单选题","矿山建设工程的安全设施竣工后，由（ ）验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设行政主管部门",false,{"key":16,"text":17,"correct":18},"B","管理矿山企业的主管部门或煤矿安全监督管理部门",true,{"key":20,"text":21,"correct":14},"C","矿山企业",{"key":23,"text":24,"correct":14},"D","工程质量监督机构","P266-268 1.矿山建设工程应当按照经批准的设计文件施工，保证施工质量;工程竣工后，应当按照国家有关规定申请验收。建设单位应当在验收前60日向管理矿山企业的主管部门、劳动行政主管部门报送矿山建设工程安全设施施工、竣工情况的综合报告。2.管理矿山企业的主管部门（煤矿安全监督管理部门）、劳动行政主管部门应当自收到建设单位报送的矿山建设工程安全设施施工、竣工情况的综合报告之日起30日内，对矿山建设工程的安全设施进行检查;不符合矿山安全规程、行业技术规范的，不得验收，不得投入生产或者使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]