[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123677,791,1,"单选题","矿井建设期间为综合平衡的“四个排队”中，规模、影响、范围最大是（ ）的排队。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","矿建、土建和机电设备安装工程间",true,{"key":16,"text":17,"correct":18},"B","设备间",false,{"key":20,"text":21,"correct":18},"C","年度计划与季度计划",{"key":23,"text":24,"correct":18},"D","多工序间","P120-122 在矿井建设期间，必须做好\"四个排队\"和\"六个协调\"。所谓\"四个排队即:井巷、土建和机电设备安装工程的总排队;设备进场计划排队（包括提出设备到货的具体要求，以及到货日期的可能误差）；年度计划与季度计划排队;多工序间的排队。为了使\"四个排队\"切实可行，必须做到\"六个协调即:设计图纸到达日期必须与施工的需要相协调;设备到达现场日期必须与安装工程的需要协调;材料供应必须与工程进度协调；各工序的交替时间必须相互协调;投资拨款与工程需要相协调;劳动力的培训与调配必须与工程进度协调。矿山建设工程是一项复杂的系统工程，通常包括矿建、土建、安装三大工程内容。在施工的各个阶段，都要围绕关键线路的关键工程组织快速施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]