[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123669,791,1,"单选题","某矿建公司通过招投标方式承担立井井筒的施工任务，工期为18个月。为了在18个月内完成施工任务，该矿建公司应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增加大型施工设备",false,{"key":16,"text":17,"correct":14},"B","大量增加工作面的施工人员",{"key":19,"text":20,"correct":21},"C","狠抓关键工程的施工",true,{"key":23,"text":24,"correct":14},"D","狠抓所有工程的施工","P104-108 施工是基本建设程序中的一个重要环节，它是落实计划和设计的实践过程。工程施工要遵循合理的施了顺序，特别是前期方案的制定，矿建、土建、机电安装三类工程的衔接，狠抓关键工程的施工，确保工程按期高质量地完成。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]