[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123663,791,1,"单选题","矿井项目的施工准备阶段，一般应以安排（ ）为主。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","地面永久工程准备",false,{"key":16,"text":17,"correct":14},"B","矿井工业广场购地",{"key":19,"text":20,"correct":21},"C","井筒开工准备",true,{"key":23,"text":24,"correct":14},"D","矿井永久安装工程准备","P110-111 施工准备期应以安排井筒开工以及项目所需要的准备工作为主，要在施工初期适当利用永久工程和设施，如行政联合福利建筑、生活区建筑变电站、供水、供暖、公路、通信等工程，并尽量删减不必要的临时工程，以减少大型临时工程投资和改善建井初期施人员的生活条件;但过多地用永久建筑将增加建井初期的投资比重因此，要对工程项目投资时和大临工程投资进行综合分析，选择最佳效益。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]