[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123662,791,1,"单选题","当矿井工业场地布置有主、副井两个井筒时，对于井筒的施工顺序，我国多采用（ ）的方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主井比副井先开工",true,{"key":16,"text":17,"correct":18},"B","副井比主井先开工",false,{"key":20,"text":21,"correct":18},"C","主井与副井同时开工",{"key":23,"text":24,"correct":18},"D","主井与副井交替开工","P114-120 对于主副井井筒在同一工业广场内的立井开拓项目，我国多采用主井比副井先开工的方式。因为在一般情况下，主井比副井深，又有装载硐室，施工要占一定工期。主井先开工，基本和副井到底的时间前后相差不大，然后从主副井两个方向同时进行短路贯通，其最大的好处是贯通时间快，独头掘进距离短。特别是后续以吊桶提升的临时改绞前的时间段，人员上下、运输转载等都比较复杂。所以，主井提前开工有利于尽快完成临时提升系统改装，加大提升能力，缩短主副井交替装备的工期（先临时改装主井提升，然后再进行副井永久提升装备）。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]