[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123634,791,1,"单选题","排土场必须分期进行（ ），如排土场有可能发生滑坡和泥石流等灾害的，必须进行稳定处理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","渣土堆放",false,{"key":16,"text":17,"correct":14},"B","表面封闭",{"key":19,"text":20,"correct":21},"C","覆土植被",true,{"key":23,"text":24,"correct":14},"D","安全防护","P259-260 排土场必须分期进行覆植被。如排士场有可能发生滑坡和泥石流等灾害的，必须进行稳定处理。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]