[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123601,791,1,"单选题","关于不可抗力事件中，施工单位进场的机械、设备受到损坏以及工期的损失，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","机械设备损失由业主承担，工期不顺延",false,{"key":16,"text":17,"correct":14},"B","机械设备损失由业主承担，工期顺延",{"key":19,"text":20,"correct":21},"C","机械设备损失由施工单位承担，工期顺延",true,{"key":23,"text":24,"correct":14},"D","机械设备损失由施工单位承担，工期不顺延","P207-210 可抗力事件导致的费用，发、承包双方应按以下原则分别承担并调整工程价款（1）合同工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工现场用于施工的材料和l待安装的设备的损害，由发包人承担;（2发包人、承包人人员伤亡由其所在单位负责，并承担相应费用;（3）承包人的施工机械设备的损坏及停工损失，由承包人承担;（4）停工期间，承包人应发包人要求留在施工现场的必的管理人员及保卫人员的费用由发包人承担;（5）工程所需清理、修复费用，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]