[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123596,791,1,"单选题","矿业工程施工承包人在工程变更确定后（ ）内，提出变更工程价款的报告，经工程师确认后调整合同价款，否则，视为该项变更不涉及合同价款的变更。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7d",false,{"key":16,"text":17,"correct":18},"B","14d",true,{"key":20,"text":21,"correct":14},"C","28d",{"key":23,"text":24,"correct":14},"D","30d","P207-210 承包人首先在工程变更确定后1 4 d内，提出变更工程价款的报告，经工程师确认后调整合同价款，在双方确定变更后1 4 d内承包人不向工程师提出变更工程价款报告的，视为该项变更不涉及合同价款的变更。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]