[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123595,791,1,"单选题","计算变更工程应采用的费率或价格，如果实施变更工作未导致工程施工组织和施工方法发生实质性变动，（ ）该项目的单价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","局部调整",false,{"key":16,"text":17,"correct":14},"B","全部调整",{"key":19,"text":20,"correct":14},"C","重新确定",{"key":22,"text":23,"correct":24},"D","不应调整",true,"P207-210 变更工作在工程量表中有同种工作内容的单价，应以该费率计算变更工程费用。实施变更工作未导致工程施工组织和施工方法发生实质性变动，不应调整该项目的单价。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]