[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123588,791,1,"单选题","矿业工程施工中，关于索赔与变更的不正确表述是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","索赔和变更都处理原合同上没有的内容或没有正常执行的内容",false,{"key":16,"text":17,"correct":14},"B","变更通常是在施工前或施工过程中，索赔通常是在施工过程甚至更晚的时候",{"key":19,"text":20,"correct":14},"C","变更可能引起索赔，但不是一定引起索赔",{"key":22,"text":23,"correct":24},"D","索赔和变更总是同时发生和存在的",true,"P207-210 索赔是工程承包中经常发生的正常现象。由于施工现场条件、气候条件的变化，施工进度、物价的变化，以及合同条款、规范、标准文件和施工图纸的变更、差异、延误等因素的影响，使得得工程承包中不可避免地出现索赔。施工合同变更，是指合同成立以后履行完毕以前双方当事人对合同的内容进行的修改。合同价款、工程内容、工程的数量、质量要求和标准、实施程序等一切改变都属于合同变更。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]