[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123582,791,1,"单选题","从可行性研究、勘察设计、组织施工、设备订货、职工培训直到竣工验收，全部工作交由一个承包公司完成，这种承包方式称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专项承包",false,{"key":16,"text":17,"correct":14},"B","项目承包",{"key":19,"text":20,"correct":21},"C","项目总承包",true,{"key":23,"text":24,"correct":14},"D","阶段承包","P196-197 项目总承包即从可行性研究、勘察设计、组织施工、设备订货、职工培训直到竣工验收，全部工作交由一个承包公司完成。这种承包方式要求项目风险少、承包公司有丰富的经验和雄厚的实力。目前，它主要适用于洗煤厂、机厂之类的单项工程或集中住宅区的建筑群。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]