[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123581,791,1,"单选题","按照项目实施的先后进行招标的方式称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总承包",false,{"key":16,"text":17,"correct":18},"B","阶段承包",true,{"key":20,"text":21,"correct":14},"C","分承包",{"key":23,"text":24,"correct":14},"D","独立承包","P196-197 2.分阶段平行承发包这是把矿业工程项目某些阶段或某一阶段的工作分别招标承包给若干单位。如把矿井建设分为可行性研究、勘察设汁、施工、培训等几个阶段分别进行招标承包。这是目前多数项目采用的原包方式。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]