[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123567,791,1,"单选题","矿业工程成本管理，不可作为竞争性费用的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","二次搬运费",false,{"key":16,"text":17,"correct":18},"B","安全文明施工费",true,{"key":20,"text":21,"correct":14},"C","冬雨期施工增加费",{"key":23,"text":24,"correct":14},"D","夜间施工增加费","P188-189 措施项目中的总价项目计价应根据招标文件及拟建工程的施工组织设计或施工方案确定。措施项目中的安全文明施工费必须按国家或省级、行业建设主管门的规定计算，不得作为竞争性费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]