[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123566,791,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，招标工程量清单的准确性与完整性应由（ ）负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标人",false,{"key":16,"text":17,"correct":14},"B","招标人指定的招标代理机构",{"key":19,"text":20,"correct":14},"C","招标人的上级部门",{"key":22,"text":23,"correct":24},"D","招标人",true,"P188-189 建设工程发承包及实施过程的不同阶段，可分别称为招标工程量清单、已标价工程量清单等。招工程量清单应由具有编制能力的招标人或受其委托、具有相应资质的工程造价咨询人编制，由分部分项工程项目清单、措施项目清单、其他项目清单、规费项目清单和1税金项目清单组成。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]