[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123562,791,1,"单选题","矿业工程项目的投资由建筑安装工程费、（ ）、工程建设其他费和预备费等组成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备及工器具购置费",true,{"key":16,"text":17,"correct":18},"B","施工机具使用费",false,{"key":20,"text":21,"correct":18},"C","措施费",{"key":23,"text":24,"correct":18},"D","税金","P181-186 矿业工程项目的投资由建筑安装工程费，设备及工揣器具购置费，工程建设其他费、预备费、建设期利息等组成，而矿业工程施工成本则主要指主建筑安装费。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]