[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123541,791,1,"单选题","钢支撑预加压力施工中，支撑安装完毕后，应及时检查各节点的连接状况，经确认符合要求后可施加预压力，预压力的施加应在支撑的（ ）进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","前端",false,{"key":16,"text":17,"correct":14},"B","后端",{"key":19,"text":20,"correct":21},"C","两端同时",true,{"key":23,"text":24,"correct":14},"D","两端分别","P164-166 钢支撑预加压力的施工应符合下列要求:1）支撑安装完毕后，应及时检查各节点的连接状况，经确认符合要求后可施加预压力，预压力的施加应在支撑的两端同步对称进行;2）预压力应分级施加，重复进行，加至设计值时，应再次检查各连接点的情况，必要时应对节点进行加固，待额定压力稳定后锁定。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]