[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123537,791,1,"单选题","深基坑支护水泥土桩应在施工后（ ）进行开挖检查或采用钻孔取芯等手段检查成桩质量，若不符合设计要求应及时调整施工工艺。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一周内",true,{"key":16,"text":17,"correct":18},"B","十天内",false,{"key":20,"text":21,"correct":18},"C","半月内",{"key":23,"text":24,"correct":18},"D","一月内","P164-166 水泥土桩应在施工后一周内进行开挖检查或采用钻孔取芯等手段检查成桩质量，若不符合设计要求应及时调整施工工艺。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]