[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123519,791,1,"单选题","将地面皮带运输走廊选作质量控制点的原因是该工程属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程",false,{"key":16,"text":17,"correct":18},"B","关键部位",true,{"key":20,"text":21,"correct":14},"C","施工的薄弱环节",{"key":23,"text":24,"correct":14},"D","采用新技术的部位","P146-148 矿井井筒锁口，井壁壁座，井筒与巷道连接处，巷道交岔点，提升机滚筒，提升天轮，地面皮带运输走廊，基坑支撑或拉锚系统等。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]