[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123512,791,1,"单选题","在矿山井巷工程中,不应列入关键路线的工程内容,通常是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主井或副井",false,{"key":16,"text":17,"correct":14},"B","主、副井联络巷",{"key":19,"text":20,"correct":14},"C","井底车场重车线",{"key":22,"text":23,"correct":24},"D","管子道",true,"P127-128 矿山井巷工程的内容包括井筒、井底车场巷道及硐室、主要石门、运输大巷及采区巷道等，其中部分前后连贯的工程构成了全矿井延续距离最长，施工需时最长的工程线路，被称为总进度计划图表上的关键路线。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]