[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123511":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123511,791,1,"单选题","某立井井筒净直径为6．5m，深度为750m，其中表土段深度为150m，则该井筒表土段应当采用（ ）施工，才能确保井筒的施工安全，并获得可靠的进度指标。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","井圈背板普通法",false,{"key":16,"text":17,"correct":14},"B","吊挂井壁法",{"key":19,"text":20,"correct":14},"C","板桩法",{"key":22,"text":23,"correct":24},"D","冻结法",true,"P133-136 矿业工程施工技术随着科学技术的发展丧也在不断进步，优化施工方案或采用先进的施工技术，可以有效地缩短短施工工期。如井筒表土施工，采用冻结法可确保井筒安全通过表土层，避免发生施工安全事故。井筒全深冻结施工，可有效保证井筒顺利通过基岩含水层，确保井筒的计划工期，避免了由于井筒治水而发生工期延误的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]