[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123509,791,1,"单选题","矿井竣工工期（或建井工期）是指从项目正式开工之日起到按照设计规定（ ），并经过试生产，试运转后正式交付生产所经历的时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工人员进场",false,{"key":16,"text":17,"correct":18},"B","竣工完成建设工程",true,{"key":20,"text":21,"correct":14},"C","开始场内施工准备工作",{"key":23,"text":24,"correct":14},"D","施工许可证办理完毕","P127-128 矿业工程建井工期的概念:矿井从完成建设用地的征购工作，施工人员进场，开始场内施工准备工作之日起，至项目正式开工为止称为施工准备期。从项目正式开工（矿井以关键路上任何一个井筒破土动工）之日起到部分工作面建成，并经试运转，试生产后正式投产所经历的时间，为矿井投产工期。从项目正式开工之日起到按照设计完成规定的建设内容，并经过试生产，试运转后正式交付生产所经历的时间称为矿井竣工工期（或建井工期）。矿井施工准备工期与矿井竣工工期之和构成矿井建设总工期（或称建井总工期）。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]