[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123508":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123508,791,1,"单选题","与网络进度计划相比，横道图进度计划的主要特点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能明确反映各项工作之间的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","能反映各项工作的机动时间",{"key":19,"text":20,"correct":21},"C","能直观反映各项工作的开始、完成时间",true,{"key":23,"text":24,"correct":14},"D","能正确反映出决定工期的关键工作","P128-131 与横道图计划相比，网络图计划的主要特点是:（1）网络图计划能够明确表达各项工作之间的逻辑关系。（2）通过网络计划时间参数的计算，可以找出关键线路和关键工作。（3）通过网络计划时间参数的计算，可以明确各项工作的机动时间。（4）网络图计划可以利用电子计算机进行计算、优化和调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]