[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123507":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123507,791,1,"单选题","矿井施工准备工期与矿井竣工工期之和构成矿井建设的总工期，矿井建设的总工期一般可依据（ ）来进行推算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键生产系统的施工工期",false,{"key":16,"text":17,"correct":14},"B","全部生产系统的安装工期",{"key":19,"text":20,"correct":21},"C","矿井建设的关键线路工期",true,{"key":23,"text":24,"correct":14},"D","全部土建工程的施工工期","P127-128 二、矿业工程建井工期的确定方法矿业工程建井工期的确定主要根据关键线路上工序的时间进行推算，具体方法见表2G320031。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]