[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123506,791,1,"单选题","矿业工程施工进度计划编制时，网络计划工作的重点是确定（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方案",false,{"key":16,"text":17,"correct":14},"B","施工方法",{"key":19,"text":20,"correct":14},"C","施工技术",{"key":22,"text":23,"correct":24},"D","施工顺序",true,"P128-131 矿业工程利用网络图来表示进度计划，适应了目前建设行业的发展趋势，利用网络图进度计划，可以使矿业工程施工进度得到有效控制。实践己证明，网络图进度计划是用于控制工程进度的最有效工具。根据矿业工程项目施工的特点，目前施工进度计划主要采用确定型网络计划中的时标网络计划，它以时间坐标为尺度表示各项工作进度的安排，工作计划时间直观明了。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]