[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123505,791,1,"单选题","矿业工程项目在确立施工进度目标时，施工方案选择的一般要求是工程应有较先进的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键进度指标",false,{"key":16,"text":17,"correct":18},"B","平均进度指标",true,{"key":20,"text":21,"correct":14},"C","施工技术水平",{"key":23,"text":24,"correct":14},"D","施工质量目标","P128-131 保证施工安全和质量要求的条件下，考虑技术先进性，以及经济效益条件。一般要求施工方案应有较先进的平均进度指标。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]