[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123504,791,1,"单选题","矿业工程进度计划编制时，对矿山工程施工要特别注意（ ）的施工顺序。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","井筒与相互毗连的硐室",false,{"key":16,"text":17,"correct":14},"B","关键线路上工程",{"key":19,"text":20,"correct":21},"C","主、副井井筒交替装备",true,{"key":23,"text":24,"correct":14},"D","矿井与土建工程","P131-133 组织矿井建设关键线路上的井巷工程的施工;主副井交替装备的施工;井巷、硐室与设备安装交叉作业的施工;采区巷道与采区设备安装交叉作业的施工;按照立体交叉和平行流水作业的原则织井下及地面施工与安装。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]