[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123503,791,1,"单选题","工程进度更新的主要工作有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析进度偏差的原因",true,{"key":16,"text":17,"correct":18},"B","投入更多资源加速施工",false,{"key":20,"text":21,"correct":18},"C","调整施工合同",{"key":23,"text":24,"correct":18},"D","修改设计","P133-136 矿业工程施工项目进度控制，其控制内容包括事前阶段的进度控制、事中阶段工期控制和事后进度控制。在项目的具体实施过程中，项目管理人员要实时掌握进度计划的实际执行情况，发现进度计划出现偏差，应及时分析偏差产生的原因，并且采取有效措施，对进度计划进行调整，然后实施调整后的进度计划，确保施工进度在掌控之内。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]