[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123502,791,1,"单选题","矿山工程进度拖延的事后控制措施最关键的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析进度拖延的原因",true,{"key":16,"text":17,"correct":18},"B","投入更多资源加速施工",false,{"key":20,"text":21,"correct":18},"C","调整施工合同",{"key":23,"text":24,"correct":18},"D","修改设计","P49 进度拖延的事后控制措施最关键的是要分析引起拖延的原因，通常有以下措施:（1）对引起进度拖延的原因采取措施;（2）投入更多的资源，加快施工进度;（3）采取措施保证后期工程的施工按计划执行;（4）分析进度网络，找出有工期延迟的路径;（5）征得业主的同意后，缩小工程的范围，包括减少工作量或删去一些工作（或分项工程）。（6）改进方法和|技术，提高劳动生产率;（7）采用外包策略，让更专业的公司用更快的速度、更低的成本完成一些分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]