[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123499,791,1,"单选题","某矿施工网络图见图2G320030—1，则该网络计划的总工期是（ ）d。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","80",false,{"key":16,"text":17,"correct":14},"B","85",{"key":19,"text":20,"correct":21},"C","90",true,{"key":23,"text":24,"correct":14},"D","95","P128-131 矿业工程利用网络图来表示进度计划，适应了目前建设行业的发展趋势，利用网络图进度计划，可以使矿业工程施工进度得到有效控制。实践己证明，网络图进度计划是用于控制工程进度的最有效工具。根据矿业工程项目施工的特点，目前施工进度计划主要采用确定型网络计划中的时标网络计划，它以时间坐标为尺度表示各项工作进度的安排，工作计划时间直观明了。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]