[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123497,791,1,"单选题","矿业工程进度计划编制的基本程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查研究、确定方案、划分工序并估算时间、绘制进度计划图表",true,{"key":16,"text":17,"correct":18},"B","调查研究、确定方案、分组编制、总体合成",false,{"key":20,"text":21,"correct":18},"C","调查研究、划分项目、确定方案、分组编制、总体合成",{"key":23,"text":24,"correct":18},"D","调查研究、划分项目、确定方案、划分工序、计算时间、编制计划、审查计划、确定计划","我的答案：未作答 收藏本题 纠错 收起解析 暂无解析",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]