[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1123495,791,1,"单选题","下列进度控制措施中，属于组织管理措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","优选施工方案",false,{"key":16,"text":17,"correct":14},"B","采用新技术、新工艺",{"key":19,"text":20,"correct":21},"C","加强总包与分包单位间的协调工作",true,{"key":23,"text":24,"correct":14},"D","编制资源需求计划","P131-133 组织管理措施:1.选择一个强有力的监理单位。矿井建设过程中，建设单位应当选择一个强有力的监理单位，以便矿井建设过程中实施工程进度、质量、投资的有控制，协调好建设单位与施工单位之间的各项关系和矛盾。 2.搞好综合平衡协调。由于关键线路并不是固定不变的，在施工过程中，随着客观条件和工程实际进度的变化，关键线路也可能随之变化。因此，搞好三类工程进度的综合平衡，避免关键线路的转化，对加快工程进度十分必要。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]