[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123487,791,1,"单选题","硐室全断面施工法和普通巷道施工法基本相同，硐室全断面施工法一般适用于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","稳定及整体性好的岩层",true,{"key":16,"text":17,"correct":18},"B","稳定性较好岩层",false,{"key":20,"text":21,"correct":18},"C","不稳定岩层",{"key":23,"text":24,"correct":18},"D","完整性岩层","P82-85 全断而施工法和普通巷道施工法基本相同。在常规设备条件下，全断面一次掘进硐室的高度，一般不得超过4-5m。这种施工方法一般适用于稳定及整体性好的岩层。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]