[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123485":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1123485,791,1,"单选题","当地质条件复杂且硐室断面特大时，通常采用（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","全断面施工法",false,{"key":16,"text":17,"correct":14},"B","分层施工法",{"key":19,"text":20,"correct":14},"C","分次施工法",{"key":22,"text":23,"correct":24},"D","导硐施工法",true,"P82-85 对地质条件复杂或者断面特大的硐室，为了易于控制顶板和尽早砌筑墙壁，或为解决出矸、通风等问题，可先掘进1-2个小断面巷道（导硐），然后再刷帮、挑顶或卧底，将硐室扩大到设计断面。一般反向施工交叉点时宜采用导硐施工法。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]