[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1123477,791,1,"单选题","巷道掘砌循环图表在编制时要考虑（ ）的备用时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10％",true,{"key":16,"text":17,"correct":18},"B","20％",false,{"key":20,"text":21,"correct":18},"C","30％",{"key":23,"text":24,"correct":18},"D","40％","P86-87 为防止难以预见的工序延期，提高循环图表完成的概率，应考虑加10%的备用时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]