[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123455,791,1,"单选题","立井井筒掘砌混合作业区别于短段单行作业的主要特征是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将井筒划分为若干段高，自上而下逐段施工",false,{"key":16,"text":17,"correct":18},"B","浇筑混凝土的同时即可装岩出渣",true,{"key":20,"text":21,"correct":14},"C","在同一段高内，按照掘、砌先后交替顺序作业",{"key":23,"text":24,"correct":14},"D","砌壁是在多层吊盘上，自上而下逐段进行的","P69-74 井筒掘、砌工序在时间上有部分平行时，称混合作业。它既不同于单行作业（掘、砌顺序完成），也不同于平行作业（掘、砌平行进行）。混合作业是随着凿井技术的发展而产生。这种作业方式区别于短段单行作业。对于短段单行作业，掘、砌工序顺序进行;而混合作业，是在向模板浇筑混凝土达1m高左右时，在继续浇筑混凝土的同时，即可装岩出渣。待井壁浇筑完成后，作业面上的掘进工作又转为单独进行，依此往复循环。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]