[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1123454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1123454,791,1,"单选题","立井井筒施工采用短段掘砌单行作业方式时，现浇混凝土井壁施工一般采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","木模板",false,{"key":16,"text":17,"correct":18},"B","金属伸缩式活动模板",true,{"key":20,"text":21,"correct":14},"C","整体滑升金属模板",{"key":23,"text":24,"correct":14},"D","金属拆卸式模板","P79-81 金属伸缩式活动模板一般由2-3块组成，块与块之间设伸缩缝，最简单的可只设一个伸缩缝，立模和脱模可利用伸缩缝的撑开和收缩来进行。目前一般采用液压脱模，模板刚度较大，高度可采用短段掘砌的段高，这种模板目前主要用于井下工作面的混凝土井壁浇筑工作，应用效果好。",{"id":6,"name":27,"category":28,"favorite":29},"二建矿业工程实务","建筑工程",0]